Hulaki Marga construction still incomplete after five deadline extensions

No ads found for this position

Hulaki Marga road stretch between Orali bazaar and Rajapur bazaar in Bardia. Photo: Simon Paudel/ DCnepal


Kathmandu, April 6. Construction of the Hulaki Marga aka the Postal Highway here has not been completed even after six years of the deadline. 

The construction of 62 kilometers section of the highway from Dokebazaar to Bedkot of Kanchanpur district should have been over in 30 months had the construction works moved ahead smoothly. The contract for this was signed in March 2017.

Twenty-six kilometers of the section of the highway in Kanchanpur district remain to be blacktopped. The engineer at the Hulaki Highway Project Office, Deepak Sunar accepted that there has been a delay in the construction of the highway.

“The delay was due to the COVID-19 pandemic and taking approval from the National Park Office. The construction is not complete yet even after extending the deadline for five times,” he said. 

Construction of 62 kilometers of the Hulaki Road was begun after awarding the contract in three phases. The first phase included the 20 kilometers of road construction from Dokebazaar to Belauri. Ninety percent work has been completed on this section. However, the construction remains uncompleted in the remaining two sections.

The Sharma-Rajendra JV had been awarded the contract for the construction of the road in the first package at a cost of Rs 364.7 million. 

The estimated cost for the construction of the 20 kilometers road from Belauri to Beldandi under the second package is Rs 414.1 million. Only nine kilometers of the road in this section has been blacktopped so far, Sunar said. The construction has halted at the Chui area on this section due to the obstruction from the Indian side. The Indian security bodies have obstructed blacktopping the road in this location claiming the road lies within the Indian territory. 

The Babahansa Siddhisai JV, the construction company responsible for carrying out the construction under the second package, has hardly completed 50 percent of the work.

Similarly, only eight and a half kilometers of the 22-kilometer section of the highway from Beldandi to Daiji has been blacktopped under the third package in a span of six years.

“The deadline for completing the works under the second and third packages has been extended till mid-July this year. Only 36 kilometers of the highway has been asphalted in six years since the deadline was last extended,” Sunar lamented. 

The local municipalities through which the road passes have been exerting pressure from time to time for the timely completion of the construction works.

Except for the headline and the cover photo, this story has not been edited by DCNepal staff and is published from a syndicated feed by National News Agency.

 

No ads found for this position

Facebook Comment


Leave a Reply

Your email address will not be published. Required fields are marked *

Related News

latest Video